Current Construction Activities

Here is what the contractor is working on... 

Winter 2009-2010

  • Complete forming and pouring Pohopoco Creek Bridge pier stems, caps
  • Continue rock wall excavation on the southbound Turnpike shoulder at south end of work zone.
  • Construct abutments for Phopoco Creek Bridges.
  • Construct abutmets for Lehigh River Bridges.
  • Begin drilling Lehigh River Bridges pier foundations (19 total).
  • Continue retaining wall construction along the southbound lanes at north end of the work zone.

 

 

 

 